Publication Abstract




Proceedings-DFI/EFFC 11th International Conference on Piling and Deep Foundations, 2014, Stockholm, Sweden, (DFI)

Execution of Pile Installation in Environmentally Challenging Sites
Emre Biringen, Sweden; Dena Morgan, Bechtel Power Corporation, USA

This paper discusses the execution of pile installation and design issues at two environmentally challenging industrial sites in North America. Environmental regulations set constraints on the design and require versatility in choice of technology. For a proposed bridge, due to protected fish habitat, performing soil borings within 30 m of the creek embankment was prohibited. The limited subsurface profile indicated a thick upper layer of granular material, thus driving H-piles was considered. However, to limit generation of vibration and noise in the protected area, drilled piles had to be used. During execution, the subsurface profile differed from that in the borings 30 m away. Very soft, saturated silt was encountered at the bottom of the caisson and the length had to be redesigned very quickly while the contractor waited for instruction. For a new structure in uncontrolled fill area, performing soil borings was not allowed. It was known that a layer of peat was present in the area, but no information regarding the thickness and extent. The subsurface profile generally consisted of granular material overlying a thick compressible silt layer. Somewhere within the granular layer peat would likely be encountered. Franki piles were chosen to penetrate the peat and bear in the underlying granular material. During environmental sampling in the area, methane gas was encountered and Franki piles were no longer a viable option due to safety concerns. The foundation system was changed to steel H-piles driven to bedrock, which was more than 50 m below the ground surface and sloping. Rock shoes that would work to significant slopes 1had to be used in order to increase the likelihood of good embedment within the bedrock. Also, due to obstruction of an approximately 3 m thick debris field that was encountered in the upper granular soils, some of the piles had to be relocated and extra piling needed to compensate for such differences. The results of PDA testing to estimate compressive capacity and a series of lateral load tests are presented.


 article #1895; publication #100 (IC-2014)