Publication Abstract




Proceedings of the 39th Annual Conference on Deep Foundations, 2014, Atlanta, GA, USA, (DFI)

Cost Effective Drilling Of Extra Large [XL] Monopile Foundations
Phil Wilkinson and Sam Whitaker, Fugro Seacore Ltd.

The installation of large (XL) diameter monopiles offshore typically requires expensive and specialist plant, equipment and vessels. Due to the increasing size (weight, diameter and length) of the foundations, in order to mitigate installation risk, the use of large diameter drills is becoming an increasing requirement. Project developers often try to avoid drilling operations due to the time associated with the drilling process. This restricts projects in terms of location and it also overlooks the additional engineering benefits drilling can bring to monopile foundation design e.g. reduced foundation material and better fatigue design life. By comparing the lessons learned of three milestone overwater drilling projects; methods of maximising drill speed and decreasing drilling process time is established. Particular emphasis is put on pile internal relief drilling in a process known as Drive-Drill-Drive (DDD). The milestone overwater drilling projects are North Hoyle Offshore Wind Farm (OWF) (2003); Flamanville EPR cooling water outlet shaft (2008); and Gwynt-y-Mor OWF (2014). By evaluating the effect of foundation pile diameter on drilling process times, example foundation installation costs are derived and used to show that incorporating drilling as part of a process may not be cost prohibitive to projects Continued advances in drill technology, and drilling rates of penetration, combined with an integrated approach to foundation design, challenge whether hammering only is always the optimal solution for XL monopile installation.


 article #2000; publication #1011 (AM-2014)