Fraser Heights Bridge Comparison between PDA Tests and Pile Capacity Estimation Methods
Ali Azizian, Brian Hall

Driven piles were selected to support the Fraser Heights Bridge bents. Piles were a key component of the top-down construction approach, which was adopted for minimizing potential impacts on an environmentally sensitive wetland. Project requirements manda